Construction technology process of mixed type plastic
runway
1.Make waterproof processing for the concrete, after *4 hours for
maintenance, we can pave the bottom of runway.
2.The products ratio of PU-A and PU-B is 1:5, the catalyst is 1% of
total dosage of PU. The runway substrate is according to
international standard mixed with *5%**0% high elasticity black
colloidal particles with particle size of **4mm, after mixing well,
then pour them into ground and make it smooth. The laying thickness
is ***0mm. Then keep *4hours for maintenance&solidifying.
3.The proportion of finishing paint A material on runway and B
material is 1:3. And mixing them well for following use. Then
mixing EPDM with particle size of **2mm and surface paint well,
with proportion of 1:1, then pour them into paver. Let spray gun's
angle keep *0 degree for spraying. After finishing spraying, we
need *4hour for solidifying&maintenance. Spraying the runway in
the opposite direction again. The recommended dosage of finishing
paint is 1.2kg per square, EPDM particles are 1.1kg per square, the
catalyst is 0.**2kg per square, then it still needs *4 hours
to solidify.
4.After finishing *4hours solidifying&maintenance, we
can mark line on the ground.Finishing construction of all progress,
after 7days for maintenance for the runway, we can put it into
use.
国家: | China |
型号: | - |
离岸价格: | 获取最新报价 |
位置: | - |
最小订单价格: | - |
最小订单: | 1000 Square Meter |
包装细节: | under customer's confirmation |
交货时间: | within 10-15days after confirmation |
供应能力: | 15000 Square Meter per Month |
付款方式: | T/T, L/C |
產品組 : | - |